New Construction and Renovations

Bay College is renovating more than 74,000 sq ft to create a single point of contact for academic support services and ehance pedestrian flow through the Math/Science building. In addition, the college is adding 8,645 sq ft to relocate the Library and add a donor wall to the Besse Gallery.


Calendar-Updates-Links

  • Construction Calendar
  • Updated Information
  • Important Links

Project Phases

Big Sale of Furniture & Equipment 
from Renovated Spaces

May 8 & 9   10:00AM - 5:00PM

 

Phase I: New Building Construction

     Construct new building to house Library

     April 18, 2016 - May 11, 2016
 

Phase II: Renovate LRC & MS Buildings

     Renovate the previous Library space

     Renovate the vacated TRiO and Tutoring space

     Renovate the center of the Math/Science building

     May 11, 2016 - August 8, 2016
 

Phase III: Complete Interior of New Library

     Finish the interior of the new Library

     August 8, 2016 - December 20, 2016